Levenson Project Construction Site News
1. Facade cladding work using natural stone and brass lamellas, as well as restoration of the historic facades, has been completed — 100% ready.
2. Installation of internal engineering systems, utilities, and equipment is nearing completion: ventilation, air conditioning, power supply, lighting, low-voltage systems, and automation — 90% ready.
3. Installation of elevators, service lifts, the turntable platform, and underground parking gates has been completed — 100% ready.
4. Installation of water supply and sewage systems has been completed — 100% ready.
5. Finishing work continues in the apartments, common areas, and underground parking — 40% ready.
6. Installation of natural stone cladding in apartments and common areas continues — 35% ready.
7. Installation of metal facade elements and roof parapet railings continues — 70% ready.
8. Landscaping work, along with installation of architectural and landscape lighting, continues — 60% ready.
9. Parquet flooring installation in apartments is underway — 10% ready.
10. Door installation in apartments and common areas is underway — 10% ready.